Answer:
Allocated MOH= $210,000
Explanation:
First, we need to calculate the predetermined overhead rate:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 222,000/37,000
Predetermined manufacturing overhead rate= $6 per machine hour
Now, we cal allocate overhead:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Allocated MOH= 6*35,000
Allocated MOH= $210,000